Hydrographic Survey Scope of Work That Makes Bids Comparable

A weak hydrographic survey scope of work is a common reason two bids for the same job end up far apart in price. This article lists what a tender document must state. With those items fixed, you can compare contractors on the same basis instead of choosing the lowest price.

Why the cheapest bid is often not comparable

Imagine a tender that says only "bathymetric survey of Area X". Bathymetry means measuring water depth. Each contractor must now guess the accuracy, the coverage, the depth reference, the crew and the files you want. One bidder assumes a basic check of the seabed. Another assumes full coverage with a multibeam echosounder, which maps a wide strip of seabed on every pass. The second bid costs more because it promises more.

You then compare prices, but the products are different. The fix is not a longer document. It is a document that removes the guesswork. Write down the purpose, the standard, the datum, the coverage, the proof you expect and the deliverables. Then ask each bidder to show how they will meet them.

Hydrographic survey launch from a NOAA ship working in New York Harbor
A survey launch from the NOAA Ship Thomas Jefferson working in New York Harbor. Source: NOAA National Ocean Service, via Wikimedia Commons (public domain).

Start with the purpose, then choose the standard

Begin with what the data is for. Safe navigation, berth design, dredging volumes and sediment monitoring need different quality. The purpose tells the contractor which standard and which scope apply. The New Zealand port survey guidelines list purpose first among the parameters a specification should hold [4].

The usual standard is IHO S-44, the international rulebook for hydrographic survey accuracy. The table below uses S-44 Edition 6.1.0 (October 2022). All uncertainties are at 95% confidence. THU is horizontal uncertainty. TVU is vertical uncertainty, shown here as its constants a and b. The maximum error is the square root of a² plus (b × depth)² [1].

OrderTypical useTHUTVU (a; b)Bathymetric coverage
ExclusiveShallow water, minimum underkeel clearance1 m0.15 m; 0.0075200%
SpecialBerths, ports, critical channel sections2 m0.25 m; 0.0075100%
1aCoastal water, harbours, channels5 m + 5% of depth0.5 m; 0.013100%
1bUnderkeel clearance not an issue5 m + 5% of depth0.5 m; 0.0135%
2General picture of the seabed20 m + 10% of depth1.0 m; 0.0235%

Two points matter for a tender. First, name the edition. The IHO website now lists Edition 6.2.0 (October 2024) [2]. The figures in this article come from Edition 6.1.0, so check them against the edition you cite. Indonesian standards such as SNI 7988:2014 still refer to the older S-44 Edition 5 with four orders [6]. If your tender cites both, say which one wins.

Second, one order need not cover the whole area. S-44 says the client should choose the most suitable order and define different orders across the area where needed. Its example is a deep channel surveyed to Order 1a, with any shoal shallower than 40 m surveyed to Special Order [1]. A stricter order means denser lines and more field days. That is a main driver of cost.

Datum, coverage and what to measure

A datum is the reference for positions and depths. State the horizontal datum by name and epoch. State the vertical reference too, such as Lowest Astronomical Tide. S-44 asks that tidal observations run as long as possible, preferably not less than 30 days [1]. SNI 7988:2014 also asks for at least 30 days or the survey duration [6]. A tide gauge that must run for a month changes both cost and schedule.

Next, define coverage. The smallest object the survey must detect, and the grid or bin size, should be written as numbers. The UK Civil Hydrography Programme specification gives a good model. It requires an object of 2 m to be detected in depths under 40 m, with each object hit by at least nine soundings [5]. Also say what happens where coverage fails. The same specification makes the contractor report such areas before leaving the site, using a coverage exemption form [5].

Diagram of a multibeam sonar under a ship producing a fan-shaped swath on the seabed
A multibeam system under a ship's hull covers a fan-shaped swath of seabed. Source: NOAA National Ocean Service, via Wikimedia Commons (public domain).

Ask for proof, not only promises

Do not specify the exact equipment unless you must. The UK specification is written to be equipment and software agnostic, so contractors may offer the most efficient method that meets the standard [5]. Instead, ask for a method statement. This is a document that explains how the survey will be done and how the contractor will prove the standard was met [4].

Ask each bidder for the same evidence:

A bid that includes these items cannot fairly be compared with one that leaves them out. Our article on QA/QC in hydrographic and geophysical survey data explains what good checks look like.

People, deliverables and data ownership

Fix the key person in numbers. The UK specification requires the on-site Charge Surveyor to hold a Category A course or equivalent, with at least five years of offshore experience. The CV must be approved before assignment [5]. For background, read what hydrographic surveyor certification proves.

Then list the deliverables. These usually include a report, raw and processed data, depth charts and metadata. NOAA requires grid metadata to state the coverage achieved and whether any data is interpolated [3]. Set a due date for each milestone. Tie payment to data that passes your check [5]. The guide to reading survey report deliverables as a client shows what to expect.

Finally, settle ownership and licence before the contract starts. NOAA requires data to be licensed before delivery, and restricted licences stop it using the data in charts [3]. Decide who may publish your data, and write it down.

Weather, safety and a checklist for your document

I found no formal hydrographic standard that sets a weather standby clause. As general practice, state in the tender how bad-weather days are counted. Say whether standby is paid, what sea conditions stop work, and who carries the risk. Then every bidder prices the same assumption. Even long weather records predict downtime poorly, so an agreed rule avoids later disputes [7].

Safety belongs in the document as well. The UK specification asks for a safety management plan and an emergency response plan before operations begin [5]. A practical outline for your terms of reference follows.

  1. Purpose and background.
  2. Survey area and coordinates.
  3. Standard, edition and order for each zone.
  4. Datum and control.
  5. Coverage and data density.
  6. Minimum equipment and calibration.
  7. Personnel.
  8. QA/QC.
  9. Deliverables and formats.
  10. Schedule, weather and milestones.
  11. Safety and permits.
  12. Data ownership and licence.

Write the hydrographic survey scope of work first, then compare

A clear hydrographic survey scope of work states the purpose, the S-44 edition and order, the datum, the coverage, the proof you require and the deliverables. Score bids against those items, then look at price. If you need help defining the work, see our hydrographic and bathymetric survey services.


References

  1. International Hydrographic Organization, "S-44 Standards for Hydrographic Surveys, Edition 6.1.0," IHO, October 2022, https://iho.int/uploads/user/pubs/standards/s-44/S-44_Edition_6.1.0.pdf
  2. International Hydrographic Organization, "Standards and Specifications," IHO, accessed November 2026, https://iho.int/en/standards-and-specifications
  3. NOAA Office of Coast Survey, "Hydrographic Survey Specifications and Deliverables (HSSD), Version 2026.0.01," NOAA, 2026, https://nauticalcharts.noaa.gov/publications/documents/HSSD_2026-0-01.pdf
  4. Maritime New Zealand and LINZ, "Good Practice Guidelines for Hydrographic Surveys in New Zealand Ports and Harbours," November 2020, https://www.maritimenz.govt.nz/media/qgaf4epz/hydrographic-surveys-guidelines.pdf
  5. Maritime and Coastguard Agency (UK), "UK Civil Hydrography Programme Survey Specification," June 2026, https://assets.publishing.service.gov.uk/media/6aad05292f29b388848186c4/UK_Civil_Hydrography_Programme_Survey_Specification_2026.pdf
  6. Badan Standardisasi Nasional, "SNI 7988:2014 Survei batimetri menggunakan multibeam echosounder," BSN, 2014, https://big.go.id/uploads/ebook/EBookGeospasial/33/FAIsiKatalogstandarnasionalIndonesiabidanginformasigeospasial2019.pdf
  7. W.J.M. Roberts, "Contracts, Quality Assurance and Risk in the Offshore Survey Business," International Hydrographic Review LXIV(2), July 1987, https://journals.lib.unb.ca/index.php/ihr/article/download/23392/27167/35714

Related Articles

NOAA nautical chart of Cortes Bank derived from hydrographic survey data
Survey Deliverables

Reading Survey Report Deliverables as a Client

January 3, 2024 · 5 min read

A hydrographer reviewing multibeam sonar data to build a three-dimensional model of the seafloor
Survey Data QA/QC

QA/QC in Hydrographic and Geophysical Survey Data

November 27, 2024 · 6 min read

A multibeam echosounder system, the kind of equipment a certified hydrographic surveyor is qualified to operate and calibrate
Surveyor Certification

What Does Hydrographic Surveyor Certification Prove?

September 24, 2025 · 4 min read

Ready to Start Your Project?

Consult with our Sonarfix experts to discuss your survey and data processing needs. We're here to provide the best solutions.