Platforms & Survey Operations
Marine Survey Permits in Indonesia and What to Apply for First
Marine survey permits in Indonesia are not one document. They are several approvals from different agencies, and each has its own lead time. This article maps the main layers for a beginner: defence clearance, foreign vessel rules, sailing approval, navigational warnings and conservation areas. It ends with a checklist you can use before the vessel leaves the quay.
Why a survey needs several approvals
A coastal state controls what happens in its waters. Under the UN Convention on the Law of the Sea (UNCLOS), marine scientific research in the territorial sea needs the express consent of the coastal state. In the exclusive economic zone (EEZ) and on the continental shelf, it needs the coastal state's consent too. The EEZ extends up to 200 nautical miles from the coast.
UNCLOS covers scientific research. A commercial survey for oil and gas, cables or pipelines is normally governed by national law, because it touches the coastal state's rights over resources. The Convention does not name "commercial surveys", so treat this as a reasonable reading and not as a quoted rule.
In practice, Indonesia splits the work across agencies. Defence handles security clearance. The sea transport authority handles foreign vessels and sailing approval. The research agency handles foreign researchers. The fisheries ministry and conservation managers handle protected areas. Your job is to map these layers early and run them in parallel.
Security clearance and the security officer
The central document is the Security Clearance (SC) from the Ministry of Defence. Regulation Permenhan 26/2013, amended by Permenhan 20/2020, sets the rules. Marine surveys on its list include hydrographic, geophysical and geotechnical surveys, oil and gas surveys, pipeline and cable surveys, geohazard studies, and surveys for dredging and reclamation.
The regulation calls the SC an "approval document, not a licence". It lists the activity type and location, personnel, vessel, equipment and duration. It is the final requirement before a survey starts. It also does not replace permits from other agencies. The SC itself is issued without a fee.
A Security Officer (SO) from the Ministry must be on board before work begins. The SO is insured at the survey operator's cost. Work without an SC and SO can lead to sanctions, from a written warning to withdrawal of the SO or cancellation of the SC.
Who can apply, and when
The applicant is a senior government official or a director of an Indonesian legal entity based in Indonesia. The applicant must already hold a contract, licence or cooperation agreement from the relevant authority. So the project contract comes first. A survey contractor cannot request an SC with no contractual basis.
Validity and extensions
An SC lasts up to 3 months without a break. It can be extended up to 5 times, 3 months each. An extension request is due at least 10 days before expiry. An SO assignment is limited to 30 days at sea, with one extension of up to 30 days in urgent cases. A survey that runs late can therefore cost extra time and money. Build a buffer into the contract.
Foreign vessels and foreign researchers
Most delays come from the foreign route. If the vessel flies a foreign flag, Ministry of Transport rule PM 2/2021 applies. A foreign vessel may do "other activities" only when no Indonesian-flag vessel is available. It needs a foreign vessel approval (PPKA) from the sea transport directorate before it enters Indonesian waters. The rule lists oil and gas surveys. It does not say whether hydrographic or other geophysical surveys are included, so ask the authority.
A national shipping company must apply for the PPKA and take responsibility for the vessel until it leaves. The application includes a work plan with coordinates, the contract, the charter party, class and safety certificates, and the crew list. It also needs proof that an Indonesian-flag vessel was sought. Using an Indonesian-flag vessel removes many of these steps. Our article on offshore survey vessel mobilization covers that choice.
Foreign researchers face more steps. The national research agency BRIN guide of October 2022 describes a research permit, ethical clearance, an Indonesian partner and a special visa for Indonesian waters. After the research permit, the SC request goes to the Ministry of Defence. The document list includes the operation plan, area map, vessel and equipment specifications, and crew CVs. This guide targets foreign researchers, not commercial surveys.
UNCLOS Article 248 refers to information given "not less than six months" before a research project starts. Do not count on silent consent. Start early and ask each agency for its current process.
One more rule matters for transit. A foreign survey vessel passing through Indonesian waters must keep to designated sea lanes and stow or switch off survey equipment that is not for navigation (PP 36/2002). Transit with instruments running is not innocent passage.
Sailing approval and navigational warnings
Every vessel that sails needs a Sailing Approval Letter (SPB) from the Harbour Master (Syahbandar). Shipping Law 17/2008 sets this out. The SPB is not valid if the vessel does not leave within 24 hours. It can be refused or withdrawn if safety rules are broken, including seaworthiness, manning and legal status of the vessel. So plan an SPB for each departure.
A survey vessel towing a cable or working near the seabed cannot move out of the way. COLREG, the international collision rules, classes a vessel surveying or doing underwater work as restricted in its ability to manoeuvre. Other ships must be told. The status comes from the work itself, not from a declaration.
Before sailing, a cautious approach is to send the operation plan to the local Harbour Master's office and the navigation district unit. The plan should show the area, dates, vessel and towed equipment. Ask them for the format and the minimum notice. A 2022 national report to the International Hydrographic Organization describes the wider flow. Pushidrosal collects information, prepares radio navigational warnings and passes them to Jakarta Radio for broadcast. The weekly Notice to Mariners (Berita Pelaut Indonesia) is another channel. For background on that agency, see national hydrographic offices.
Conservation areas and wildlife
If the survey enters a marine protected area, you need entry approval from the area manager. Fisheries ministry regulation 31/2020 treats research as an activity allowed with conditions in all listed park and reserve zones. That includes core zones. Conditions include holding the required permits and not disturbing protected species. Sampling needs the manager's permission and must happen outside core zones. The regulation uses the word "research". Whether a commercial engineering survey counts as research is not stated, so confirm with the manager.
For sound from seismic and other acoustic sources, ask the conservation authority which mitigation conditions apply to your area. The UK guidelines from JNCC are a common reference. They suggest a 500 m mitigation zone, a pre-shooting search and a soft start. Those are UK rules, not Indonesian law. Our article on passive acoustic monitoring explains how observers apply them.
A practical checklist for marine survey permits
- Fix the survey area (with coordinates), survey type, vessel and flag, equipment, personnel and dates.
- Confirm the contract or licence from the relevant authority. The SC depends on it.
- For foreign vessels or researchers, start the PPKA, BRIN, visa and partner steps first.
- Apply for the SC and SO. Allow for the SO's insurance and travel cost.
- If you enter a conservation area, request the manager's entry approval.
- Arrange an SPB for each departure. Send the plan to the Harbour Master and navigation unit.
- After the survey, hand over the required data to the SO, including bathymetry.
No official processing times were verified for these permits. So ask each authority for its current timeline and begin the slowest route first.
What to ask your contractor
Ask for the SC number, its validity dates and the SO's name. Ask for the SPB for each trip, the vessel certificates and the survey plan. If you enter a protected area, ask for the entry approval. Write data handover duties into the contract from the start.
The practical takeaway is simple. Marine survey permits are a chain of approvals, so list them, start the slowest ones first and keep the plan unchanged once the clearance is issued. For help with survey planning and field support, see our marine geophysical survey service.
References
- United Nations, "United Nations Convention on the Law of the Sea, Part XIII: Marine Scientific Research (Arts. 238-265)," UN Division for Ocean Affairs and the Law of the Sea, 1982, https://www.un.org/depts/los/convention_agreements/texts/unclos/part13.htm
- Menteri Pertahanan RI, "Peraturan Menteri Pertahanan Nomor 26 Tahun 2013 tentang Pengamanan Survei dan Pemetaan Wilayah Nasional," Berita Negara RI 2013 No. 1116, https://peraturan.go.id/files/bn1116-2013.pdf
- Menteri Pertahanan RI, "Peraturan Menteri Pertahanan Nomor 20 Tahun 2020 tentang Perubahan atas Permenhan 26/2013," Berita Negara RI 2020 No. 1458, https://peraturan.go.id/files/bn1458-2020.pdf
- BRIN, "Foreign Research Permit Guidelines for Foreign Science & Technology Institutions and Foreigners in Indonesia," October 2022, https://lppm.usm.ac.id/wp-content/uploads/2023/07/BukuPedomanPerizinanPenelitianAsing_FRP_Guidelinebook_Okt2022.pdf
- Menteri Perhubungan RI, "Peraturan Menteri Perhubungan Nomor PM 2 Tahun 2021 tentang Persetujuan Penggunaan Kapal Asing untuk Kegiatan Lain di Wilayah Perairan Indonesia," BN 2021 No. 74, https://peraturan.bpk.go.id/Download/162322/Permenhub%20Nomor%202%20Tahun%202021.pdf
- Presiden RI, "Peraturan Pemerintah Nomor 36 Tahun 2002 tentang Hak dan Kewajiban Kapal Asing dalam Melaksanakan Lintas Damai melalui Perairan Indonesia," https://peraturan.go.id/files/PP36-2002.pdf
- DPR/Presiden RI, "Undang-Undang Nomor 17 Tahun 2008 tentang Pelayaran," JDIH Kementerian Keuangan, https://jdih.kemenkeu.go.id/api/download/FullText/2008/17TAHUN2008UU.htm
- Pushidrosal, "National Report from Indonesia to the SWPHC-19 (Annex A)," IHO South West Pacific Hydrographic Commission, February 2022, https://iho.int/uploads/user/Inter-Regional%20Coordination/RHC/SWPHC/SWPHC19/SWPHC19-07N-National%20Report_Indonesia.pdf
- UK Maritime and Coastguard Agency, "MSN 1781 (M+F): Annex, International Regulations for Preventing Collisions at Sea (COLREG 1972, as amended)," Rule 3(g), https://assets.publishing.service.gov.uk/media/5a7ca25340f0b65b3de0a2bc/msn1781.pdf
- Menteri Kelautan dan Perikanan RI, "Peraturan Menteri KP Nomor 31/PERMEN-KP/2020 tentang Pengelolaan Kawasan Konservasi," 2020, https://peraturan.bpk.go.id/Download/151950/Permen%20KKP%20Nomor%2031%20Tahun%202020.pdf
- Joint Nature Conservation Committee, "JNCC guidelines for minimising the risk of injury to marine mammals from geophysical surveys," August 2017, https://data.jncc.gov.uk/data/e2a46de5-43d4-43f0-b296-c62134397ce4/jncc-guidelines-seismicsurvey-aug2017-web.pdf